Project Snapshot
Project Sponsor: Engineering Undergraduate Society / Faculty of Applied Science
Project Size: 10,058 ft2
Budget: $5.220 million
Occupancy: Provisional occupancy September 2015. Final occupancy November 2015.
Project Manager: UBC Properties Trust
Architect: Urban Arts
Construction Manager: Syncra
Sustainability: LEED Gold
Funding: EUS Student Fees $2.56 million; APSC Fundraising $1.91 million; APSC Contribution $0.50 million; UBC Informal Learning Space Fund $0.25 million
Project Summary
The Engineering Student Centre (ESC) is being developed by the Faculty of Applied Science (APSC) and the Engineering Undergraduate Society (EUS) propose to provide a hub for undergraduate engineering students. The ESC will replace the current EUS facility, the “Cheeze Factory”.