Project Snapshot
Budget: $360,000
Occupancy: August 2014
Project Manager: UBC Project Services – Ryan Huffman
Project Summary
The GE Jenbacher engine has been installed to provide the Bioenergy Research Demonstration Facility on Lower Mall with additional thermal capacity and fuel diversification.
Sustainable features
The new engine allows UBC to:
- Reduce electrical demand by 1.5 megawatts
- Produce 7.5% of the electricity on the Vancouver campus
- Reduce carbon dioxide emissions equal to taking 42 cars off the road