Completed projects
A selection of completed projects
-
The Nest: AMS Student Union Building (SUB)
Project Snapshot Project Sponsor: Alma Mater Society/UBC Project Size: 253,750 ft2 Budget: $106.760 million Occupancy: Provisional occupancy May 2015. Final occupancy September 2015. Project Manager: UBC Properties Trust Architect: Dialog Construction Manager: Bird Construction Sustainability: LEED Platinum Funding: AMS Student…
-
Robert H Lee Alumni Centre
Project Snapshot Project Sponsor: UBC Alumni Association Project Size: 41,700 ft2 Budget: $19.515 million Occupancy: Provisional occupancy April 2015. Final occupancy July 2015. Project Manager: UBC Properties Trust Architect: Kuwabara Payne McKenna & Blumberg with Hughes Condon Marler Architects Construction…
-
HEBB 100 seismic upgrade and theatre modernization
Project Snapshot Occupancy: October 2015 Project Manager: UBC Project Services – Darren Wong Room capacity: 375 Project Summary The catalyst for this project was the need to seismically upgrade the building for life and safety. Upgrades in addition to the…
-
Engineering Student Centre
Project Snapshot Project Sponsor: Engineering Undergraduate Society / Faculty of Applied Science Project Size: 10,058 ft2 Budget: $5.220 million Occupancy: Provisional occupancy September 2015. Final occupancy November 2015. Project Manager: UBC Properties Trust Architect: Urban Arts Construction Manager: Syncra Sustainability:…
-
Baseball Training Facility
Project Snapshot Project Sponsor: UBC Athletics & Recreation Project Size: 20,000 ft2 Budget: $3.5 million Occupancy: December 2015 Project Manager: UBC Properties Trust Architect: Michael Green Architecture Construction Manager: Kindred Construction Sustainability: LEED Gold Funding: Fully donor funded
-
Life Sciences Centre Heat Recovery Chiller
Project Snapshot Budget: $530,000 Occupancy: December 2015 Project Manager: UBC Project Services – Ryan Huffman Project Coordinator: UBC Project Services – Kevin Phelan Project Summary Project purpose: The reason for the project is to recover heat from the building, and…
-
New Greenhouse Facilities at Botanical Gardens
Project Snapshot Occupancy: March 2016 Project Manager: UBC Project Services – Jay Jethwa Project Coordinator: UBC Project Services – Luc De Beir Project Summary Project purpose: to renovate, renew & replace 2 existing greenhouses to provide up to date…
-
Academic District Energy System – Steam to Hot Water Conversion
Project Snapshot Project Sponsor: UBC Energy and Water Services Project Size: Campus-wide; 14 km pre-insulated HW pipe; 131 energy transfer stations; 52 MW HW peaking plant Budget: $88.3 million Occupancy: Phased to June 2016 Project Manager: UBC Project Services –…
-
Ponderosa Commons Phase 2
Project Snapshot Project Sponsor: UBC Student Housing & Hospitality Services; Faculty of Arts; Faculty of Education Project Size: 604,436 ft2 Budget: $165.5 million Occupancy: Phase 1 Sep-Dec 2013; Phase 2 Sep 2015-June 2016 Project Manager: UBC Properties Trust Architect: Kuwabara…
-
Orchard Commons Mixed – Use Student Housing & Vantage College
Project Snapshot Project Sponsor: Vice President, Students; Principal, Vantage College Project Size: 448,686 GSF Budget: $127,473,500 Occupancy: August 2016 Project Manager: UBC Properties Trust Architect: Perkins+Will Canada Construction Manager: Stuart Olson Sustainability: LEED Gold Number of Beds: 1,049 Project Summary…